Photocopying and Scanning is not working at Westdale Branch. We aim to fix it as soon as possible.
Daily print balances for black and white and colour printing change January 2, 2026. The new daily print balance is 40 cents. Members receive four free black and white copies or two free colour copies.
Large format and vinyl printing pricing also change on January 2. Visit https://www.hpl.ca/makerspaces for updates.
Bookmobile is off the road from December 25-27, December 31, and January 1st. Visit www.hpl.ca/bookmobile for our Holiday Schedule.
Due to the setup for the Noon Hour Concert, the Fourth Floor at Central Library will be closed on Friday, January 2. Makerspace and Newcomer Learning Centre will remain open. Floors 1-3 have spaces to work and study.
All branches close on Thursday, December 25, for Christmas. This includes branches with Extended Access.
All branches close on Sunday, December 28, 2025. This includes branches with Extended Access.
All branches close on Thursday January 1 for New Years Day. This includes branches with Extended Access.
All branches close on Friday, December 26, 2025 for Boxing Day . This includes branches with Extended Access.
All HPL Branches close early on Wednesday, December 24 at 1pm. All locations are also closed on Christmas Day, Thursday, December 25, and Boxing Day, Friday, December 26. Visit www.hpl.ca/hours for our Holiday Schedule.
All HPL Branches close early on Wednesday, December 31 at 1pm. All locations are also closed on New Year's Day, Thursday, January 1st. Regular service hours resume on Friday, January 2. www.hpl.ca/hours
Branch Study Halls are paused Friday, December 19, 2025 through Monday, January 5, 2026. Central Library Study Hall hours resume Spring 2026.
www.hpl.ca/study-halls
Bring back your borrowed library items (due Oct 1 or later) within 28 days to avoid a replacement or lost fee. We'll remove the fee when you bring back your overdue items.
Red Hill Creek Expressway Books: 1980-1981
Mountain East-West and North-South Corridor Study. Phase IV
Prepared for Delcan. Ltd.
Project H3236-G
May 30, 1980
R388.40971352 NOR CESH
Archaeological Survey and Heritage Resource Assessment. East-West/North-South Transportation Corridor. East Hamilton
DeLCan. DeLeuw, Cather, Canada. Ltd.
June 1980
R388.40971352 ARC CESH
Noise Impact Assessment regarding Mountain East-West and North-South Transportation Corridor
Regional Municipality of Hamilton-Wentworth
Prepared for Delcan by Valcoustics Canada Ltd.
October 1980
R388.40971352 NOI CESH
Geotechnical Investigation Proposed Red Hill Creek Freeway Escarpment Crossing Mount Albion Road, Hamilton, Ontario
Prepared for Delcan Ltd., Project H3402-G
November 27, 1980
R388.40971352 GEO CESH
The Red Hill Creek Issue
Glen Eker
University of Windsor
1980
R363.700971352 EKE CESH
Red Hill Creek Valley - Proposed Recreation Master Plan
Regional Municipality of Hamilton-Wentworth.
Ecologistics Ltd.
January 1981
R352.94580971 RED CESH
Mountain East-West and North-South Corridor Study. Phase 4 - Functional Planning of Preferred Option. Report 4 of 4
September 1981
R388.40971352 HAM Vol. 4 CESH
Background Reports Red Hill Expressway Consolidated Hearing - Direct Comparison of Community Response to Road Traffic Noise and the Aircraft Noise
Fred L. Hall, Susan E. Birnie, S. Martin Taylor and John E. Palmer
Department of Civil Engineering and Department of Geography, McMaster University, Hamilton, Ontario Canada.
Journal of the Acoustical Society of America 70(6)
December 1981
CA3ONHWAO5 84 B167